Activity

[Work on own experiences/completions]

Quality Assurance, Test, Usability

A-51 Test the sub system

Test the current version of one sub system. Describe the results.

Activity has to be run in Elaboration Phase (Iterative Activity)
Activity has to be run in Construction Phase (Iterative Activity)
Activity has to be run in Transition Phase (Exceptional Activity)


Run the prepared and relevant tests for one sub system. Describe the results. Check that all necessary component tests are done well.


Reasons:

Trigger:

Precondition:

Documents:

E-138 Test documentation
E-60 Test data
E-59 Testcase

Countercondition:

Results:

E-61 Test report
E-138 Test documentation

Special tools:



Responsible person:

.Project Quality Manager

Involved persons:

.Automated Test Developer
.Test Maintainer
.Test accomplisher
.Test Originator

Postcondition:

A-257 Update the test concept