E-70 Mile stone document

Belong to:

Management-results

Is part of:

E-35 Planning folder

Description:

As a mile stone specification (status "report of objectives which have to be achieved") the mile stone document includes following items:

  • countable and checkable aims and success factors that are agreed
  • if necessary, priorities and exceptions, etc.
  • signature of the project leader or person, that is responsible for the mile stone
As a mile stone report of results (status "report of results") the document includes following items:
  • short descriptions of the results that have been reached
  • valuation of the results that have been reached (with the countable and proofable aims and success factors that are agreed)
  • possible or secure effects and consequences
  • decision whether the mile stone have been reached or not
  • necessary measures, recommendation
  • overview/summarization of the experience that have been made

Result contains:

Tools:



Possible status:

  • report of objectives which have to be achieved
  • mile stone report of results

  • Producing or changing from:

    A-18 Check the mile stone achievement
    A-16 Plan iterations and deliveries
    A-302 Test the release

    Is needed for:

    A-253 Make experience report of the project
    A-16 Plan iterations and deliveries
    A-18 Check the mile stone achievement
    A-46 Define tasks for iteration i+1
    A-302 Test the release