[Work on own experiences/completions]



E-10 Effort estimation

Belong to:

Management-results

Is part of:

E-78 Preliminary study
E-35 Planning folder
E-83 Software development schedule

Description:

The list includes following items:

  • name of the estimation value
  • estimated effort in man days (PT)
  • estimation uncertainties (percentage figure)
  • author
  • remarks, etc.

Result contains:

Tools:



Possible status:

Producing or changing from:

A-249 Effort Estimation Workshop

Is needed for:

A-12 Plan the project

QS-Note:

Patter/Example:

OEP - Object Engineering Process, v2.0, 06.11.2006 11:08:31, Copyright © 2003 by oose.de eG